Final Paving Rescheduled - Friday 6/28 and Monday 7/1
Update 7/1: Today's paving has been reschedule for Wednesday, 7/3.
Final paving of roadway surfaces as part of the Powder House Boulevard and Alewife Brook Parkway Intersection Redesign has been rescheduled for Friday, June 28th and Monday, July 1.
Locations of Work and Schedule (Subject to change due to weather or other factors)
Friday 6/28 - COMPLETE
The intersection of Alewife Brook Parkway and Powder House Blvd. - extending roughly 600 feet in either direction along Alewife Brook Parkway
Monday 7/1 - RESCHEDULED TO 7/3
Powder House Blvd between North Street and Alewife Brook Parkway
Powder House Blvd and North Street intersection
The new residential shared street along Alewife Brook Parkway
Work hours are weekdays, 7 a.m. - 5 p.m.
Alewife Brook Parkway Eastbound Detour/Powder House Blvd Closure
During work hours, temporary detours and road closures will be in effect:
-
Alewife Brook Parkway
Eastbound traffic will be detoured right on Broadway, left on North Street, and left on Boston Avenue to return to Alewife Brook Parkway.
Westbound traffic will be maintained as usual.
-
Powder House Blvd (North Street to Alewife Brook Parkway)
-
Closed to through traffic
Access will be maintained for residents during milling.
-
Pedestrian access will be maintained.
Detours will be in effect during work hours only, approximately 7 a.m. to 5 p.m., on dates when milling and paving is underway.
If you have questions, please email construction@somervillema.gov or call the Engineering Division at (617) 625-6600 ext. 5400 with questions.