CONSTRUCTION UPDATE - Phase 1 Extended to Early Spring

UPDATE: Construction Phase 1

UEL Contractors will continue to work during the winter, weather permitting.

Anticipated Schedule: September - Early Spring 2024 (subject to change)

Location: On-Site - Junction Park (Centre St. to Central St.)


Description of Work:

  • Repaving Community Path between Centre St. and Central St.

  • Tree removal

  • Underground utility work

  • Look out installation

  • Light pole installation


Anticipated Impacts:

  • Community Path: During Phase 1, the Community Path will remain open and directed along the construction site. Access from Woodbine and Central street will remain open.

  • The temporary asphalt path is the same width as the Community Path extension from Central Street to Brickbottom and meets ADA accessibility requirements.