UPDATE: Junction Park - Phase 1 On-Site Community Path Route - Thursday, September 28 (subject to change)

Construction Phase 1

Anticipated Schedule: September - December 2023 (subject to change)

Location: On-Site - Junction Park (Centre St. to Central St.)


Description of Work:

  • Repaving Community Path between Centre St. and Central St.

  • Tree removal

  • Underground utility work

  • Seat wall and retaining wall installation


Anticipated Impacts:

  • Community Path: During Phase 1, the Community Path will remain open and directed along the construction site. Access from Woodbine and Central street will remain open.

  • The temporary asphalt path is the same width as the Community Path extension from Central Street to Brickbottom and meets ADA accessibility requirements.