Sidewalk Work Now Underway - August '26

As Eversource nears completion of its gas utility project, City contractors MacKay have started rebuilding sidewalks on the south (even-numbered) side of Broadway between Alewife Brook Parkway and Waterhouse Street.

Crews plan to proceed on the south side of the street toward Clarendon Avenue before transitioning to the north (odd-numbered) side of the street.

As work progresses, we will be implementing a new design that will make the street safer and more accessible for everyone. For more information on the new street design see our previous update below.

Construction Impacts

  • Work is expected to take place weekdays between approximately 7 a.m. and 4 p.m.
  • On-street parking restrictions may be required. Please observe posted signage.
  • Temporary lane shifts or detours may be in effect to facilitate work.
  • During some phases of work, MBTA bus service may be temporarily modified.
    • Prior to any changes informational signage will be posted at affected stops and at mbta.com/bus.
  • Trash/recycling pickups will not be affected.

Additional notification will be provided to community members via flyer prior to sidewalk work taking place in front of their home or business.

If you have questions, please email construction@somervillema.gov or call the Engineering Division at (617) 625-6600 ext. 5400.