College Ave Resurfacing Updates 2022
Weather permitting, City contractors will resurface College Ave. from Davis Square to Powder House Circle in the coming weeks.
Anticipated Schedule (subject to change):
May 31 - June 3: Milling the roadway, then raising cast iron structures in the street
June 6 - 10: Paving
Work hours are approximately between 7 a.m. and 5 p.m.
Pavement markings are expected to be installed later in June.
Anticipated Impacts:
Parking restrictions and periodic road closures will be required during work hours.
Some adjacent one-way streets will temporarily support two-way traffic during work hours.
MBTA bus routes 89, 94, & 96 Inbound & Outbound will offer modified service. For details, go to mbta.com/bus.
Please email construction@somervillema.gov or call the Engineering Division at (617) 625-6600 ext. 5400 with questions.