Western Washington Street Mobility Improvements
The City of Somerville is planning to reconstruct sidewalks and repave Washington Street between Webster Avenue and Line Street. As part of this effort, the City has the opportunity to explore a new design that makes it safer and more comfortable for people walking, wheeling, biking, taking the bus or driving.
The City launched a community engagement process in March 2022. A conceptual design for the street was developed over 2022 shaped by community input. The City finalized design in 2023 and initiated preliminary construction in late 2023. Construction is anticipated to be completed by the end of 2024.
Check out final design illustrations in English, Español, Português, Kreyòl Ayisyen, नेपाली, 简体中文版, 繁體中文版.
The City of Somerville is planning to reconstruct sidewalks and repave Washington Street between Webster Avenue and Line Street. As part of this effort, the City has the opportunity to explore a new design that makes it safer and more comfortable for people walking, wheeling, biking, taking the bus or driving.
The City launched a community engagement process in March 2022. A conceptual design for the street was developed over 2022 shaped by community input. The City finalized design in 2023 and initiated preliminary construction in late 2023. Construction is anticipated to be completed by the end of 2024.
Check out final design illustrations in English, Español, Português, Kreyòl Ayisyen, नेपाली, 简体中文版, 繁體中文版.
-
Nightwork (MassDOT) - Bumpus Bridge Sidewalk Repairs
Share Nightwork (MassDOT) - Bumpus Bridge Sidewalk Repairs on Facebook Share Nightwork (MassDOT) - Bumpus Bridge Sidewalk Repairs on Twitter Share Nightwork (MassDOT) - Bumpus Bridge Sidewalk Repairs on Linkedin Email Nightwork (MassDOT) - Bumpus Bridge Sidewalk Repairs linkBeginning the week of 8/5 or soon after, Massachusetts Department of Transportation (MassDOT) contractors will be performing overnight work to repair sidewalks on the deck of the Bumpus bridge along Washington Street by the Argenziano School.
Work hours are 8 p.m. to 5 a.m.
Some parking restrictions and temporary detours may be required during work hours. Please observe posted signage.
-
Continued Progress on Western Washington Street
Share Continued Progress on Western Washington Street on Facebook Share Continued Progress on Western Washington Street on Twitter Share Continued Progress on Western Washington Street on Linkedin Email Continued Progress on Western Washington Street linkCrews have been rebuilding sidewalks on the southern/even-numbered side of the street. Work has been proceeding east from Beacon Street toward Webster Avenue.
On sections of the street where we are building a sidewalk-level bike lane, crews have been installing a cobble buffer between the sidewalk and bike facility as seen in the image below (left).
Crews have also been installing a new floating bus stop (above right) near the intersection of Washington Street and Bowdoin Street.
What is a floating bus stop? A floating bus stops is a sidewalk bump outs that provide dedicated waiting and boarding areas for bus riders, while streamlining bus service and improving accessibility by enabling the bus to stop in the travel lane rather than having to pull over to the curb. Floating bus stops are separated from the sidewalk by a bike lane, eliminating conflicts between buses and bikes at stops and improving safety for people biking.
Following completion of work on the southern/even-numbered side, work will progress to the northern/odd-numbered side.
If you have questions about construction, please email construction@somervillema.gov or call the Engineering Division at 617-625-6600 ext. 5400.
-
Week of 5/6 - First New Sidewalks Poured
Share Week of 5/6 - First New Sidewalks Poured on Facebook Share Week of 5/6 - First New Sidewalks Poured on Twitter Share Week of 5/6 - First New Sidewalks Poured on Linkedin Email Week of 5/6 - First New Sidewalks Poured linkCity contractors have been hard at work over recent weeks installing new sidewalks along Washington Street. Work began at Beacon Street on the even-numbered side of the street and is proceeding east toward Webster Avenue (continuing on the even-numbered side for the time being).
The first concrete sidewalks (pictured below) were recently poured along the stretch.
The open gravel space on the left will become a raised sidewalk-level protected bicycle lane later this season.If you have questions about construction, please email construction@somervillema.gov or call the Engineering Division at 617-625-6600 ext. 5400.
-
Sidewalk Work Begins - Week of 4/15
Share Sidewalk Work Begins - Week of 4/15 on Facebook Share Sidewalk Work Begins - Week of 4/15 on Twitter Share Sidewalk Work Begins - Week of 4/15 on Linkedin Email Sidewalk Work Begins - Week of 4/15 linkCrews have been making good progress installing new drainage structures along Washingston Street over recent weeks.
Beginning as early as 4/16 or soon after, crews will begin rebuilding sidewalks. Work is scheduled to begin at Beacon Street and head east toward Calvin Street.Construction impacts:
- On-street parking will be restricted during construction.
- Please observe posted signage.
- Access to driveways may be temporarily restricted while the entrance is reconstructed.
- Notice will be provided directly to affected residents.
- Trash/recycling pick-ups and deliveries will not be affected.
If you have questions, please email construction@somervillema.gov or call the Engineering Division at (617) 625-6600 ext. 5400 with questions.
- On-street parking will be restricted during construction.
-
Preliminary Work Begins, Week of 3/10
Share Preliminary Work Begins, Week of 3/10 on Facebook Share Preliminary Work Begins, Week of 3/10 on Twitter Share Preliminary Work Begins, Week of 3/10 on Linkedin Email Preliminary Work Begins, Week of 3/10 linkBeginning as early as Wednesday, March 13 or soon after City contractors will begin preliminary work on the Western Washington St. Reconstruction and Mobility Improvements project.
Work hours are weekdays 7 a.m. to 3 p.m. Schedules are subject to change.
Initial Construction Activities
Over the coming weeks, crews will begin work by:
Setting up tree protection near future work zones to prevent trees from being damaged during construction.
Sawcutting (preliminary cutting prior to full excavation) select segments of asphalt/concrete.
Installing new drainage structures along Washington Street.
Construction Impacts
-
On-street parking may be temporarily restricted around work zones during construction.
Please observe posted signage.
Two-way traffic will be maintained during this initial phase of construction.
-
Sidewalk access may be restricted at times
However, pedestrian detours will be installed to maintain safe crossing and allow access to businesses and residences along the affected stretch.
Occasional modifications to MBTA bus routes–signage will be posted at affected stops.
Trash/recycling pick-ups and deliveries will not be affected.
If you have questions, please email construction@somervillema.gov or call the Engineering Division 617-625-6600 ext. 5400.
-
Preliminary Drainage Work - Begins 11/30 or Soon After
Share Preliminary Drainage Work - Begins 11/30 or Soon After on Facebook Share Preliminary Drainage Work - Begins 11/30 or Soon After on Twitter Share Preliminary Drainage Work - Begins 11/30 or Soon After on Linkedin Email Preliminary Drainage Work - Begins 11/30 or Soon After linkBeginning as early as tomorrow, November 30 or soon after City of Somerville’s contractors will begin installing new drainage structures along Washington St. as part of the City’s Western Washington St. Reconstruction and Mobility Improvements project.
This preliminary work will take place over the coming weeks as weather permits. After breaking for the winter, construction crews will remobilize in full force in early April along Western Washington St.
Anticipated Schedule and Locations of Work (Subject to Change):
Work hours are weekdays from 7 a.m. to 5 p.m.
-
Locations of work are along Washington St. between Line St. and Webster Ave.
Work expected to begin at the intersection of Washington St. and Caldwell Ave.
Construction Impacts:
-
On-street parking may be temporarily restricted around work zones during construction.
Please observe posted signage.
Two-way traffic will be maintained during construction.
-
Sidewalk access may be restricted at times to facilitate construction.
However, temporary sidewalks will be installed to maintain safe crossing and allow access to businesses and residences along the affected stretch.
Trash/recycling pick-ups and deliveries will not be affected.
If you have questions, please email construction@somervillema.gov or call the Engineering Division at (617) 625-6600 ext. 5400.
-
Construction Now Expected to Begin Spring ‘24
Share Construction Now Expected to Begin Spring ‘24 on Facebook Share Construction Now Expected to Begin Spring ‘24 on Twitter Share Construction Now Expected to Begin Spring ‘24 on Linkedin Email Construction Now Expected to Begin Spring ‘24 linkThe City's Engineering Division has been working over recent months with our project design consultants at Tetra Tech and our general contractors Charles Construction and D&R paving to prepare for construction on Western Washington St.
While construction was initially slated to begin this fall, we now anticipate work will begin in spring of 2024. The decision to defer construction until the spring was made in light of a number of factors including long lead-times to acquire necessary materials (e.g. granite curbing), City contractors’ engagement with other ongoing streetscape improvement projects across the city, and a desire to have work begin and continue uninterrupted through our full construction season (April through November).
While some preliminary work may still take place this fall (additional notification will be provided), construction crews will mobilize in full force in early April along Western Washington St. Additional notification will be provided to nearby residents and shared here once plans are finalized.
Thank you for your patience and understanding. If you have questions, please call the Engineering Division at 617-625-6600 ext. 5400 or email construction@somervillema.gov.
-
Construction Kick-off Update - Anticipating Fall '23 Start
Share Construction Kick-off Update - Anticipating Fall '23 Start on Facebook Share Construction Kick-off Update - Anticipating Fall '23 Start on Twitter Share Construction Kick-off Update - Anticipating Fall '23 Start on Linkedin Email Construction Kick-off Update - Anticipating Fall '23 Start linkThe City's Engineering Division is currently working with our project design consultants at Terta Tech and our general contractors Charles Construction and D&R paving to prepare for the initial phases of work along Western Washington St.
Work is currently expected to begin sometime this fall. Additional notification will be provided to nearby residents and shared here once plans are finalized.
Charles Construction and D&R Paving are also the City's general contractors on the currently ongoing Pearl St. Reconstruction and Safety Improvements Project. Crews will be working to complete that project over the coming weeks prior to beginning work on Western Washington.
Visit our Pearl St. project page for more info on that project and photos of street safety improvements being installed (including Somerville's first ever neighborhood traffic circle).Staying Informed
Below are a number of ways you can stay up to date on this project and others around the city:Sign-up for City Alerts - Receive important notifications about this project and work in your area.
Visit our new construction page - Get a comprehensive look at work across the city.
Sign-up for the City's Construction Newsletter - Receive a monthly digest on infrastructure work across Somerville.
Follow us on Twitter - Tweets about curb-cuts, culverts, and more.
-
Safety Improvements Coming to Washington Street starting in 2023!
Share Safety Improvements Coming to Washington Street starting in 2023! on Facebook Share Safety Improvements Coming to Washington Street starting in 2023! on Twitter Share Safety Improvements Coming to Washington Street starting in 2023! on Linkedin Email Safety Improvements Coming to Washington Street starting in 2023! linkInformation available in English, Español, Português, Kreyòl Ayisyen, नेपाली, 简体中文版, 繁體中文版.
The City of Somerville plans to reconstruct sidewalks and repave Washington Street between Webster Avenue and Line Street. As part of this effort, we aim to increase safety and comfort along the street by constructing wider sidewalks at bus stops, installing more raised crosswalks, and constructing protected bike lanes. We will also incorporate new trees, greenery, and benches into the project.
Background
In 2020, we implemented a pilot project on the street with paint and flexible plastic posts to provide more reliability for the Route 86 bus using short bus lanes and increasing safety for people biking with separated bike lanes. Over the next three years, we engaged community members to hear feedback, collected data, and evaluated safety and travel needs to develop a new permanent design for Washington Street.
We heard from community members about the concerns for safety for people walking, biking, and rolling. We heard the desire for improved bus facilities and more trees. We heard concerns about impacts to teacher parking. We heard advocacy for improved crosswalks and reduction in vehicle speeding.
Thank you so much to everyone who took surveys, attended meetings, sent in email comments, or spoke to us at our street pop-ups. Your feedback helped shape the proposed new designs. You can also learn more about the project by reviewing the feedback we heard, scrolling through this webpage, reviewing the survey summary reports in the documents tab, or checking out recordings of the past public meetings in the videos tab.
Proposed Final Designs
The City is proposing to install protected bike lanes on both sides of Washington Street. Protected bikeways offer the maximum comfort for people biking and have the widest appeal to riders of all ages and abilities. One side will have sidewalk-level bike lanes and the other side will be street level and protected with concrete curb barriers.
Bus stops will be expanded out into the street to provide a larger waiting area. Expanded bus stops also reduce bus delay because a bus doesn't have to pull in and out of the vehicle lane. Raised crosswalks will be constructed across Washington Street and across some adjacent side streets. New trees will be planted along the reconstructed sidewalks.
For any questions about the design, please reach out to the Mobility Division at transportation@somervillema.gov. You can come ask your questions at our upcoming street pop-up event on Wednesday, June 7, (Rain date: June 14) at Perry Park, 355 Washington Street, from 3:00pm to 6:00pm.
Separated Bike Lanes are at street level but separated from motor vehicle traffic with barriers. On Washington Street, concrete curbs with plastic flexible posts installed on top of the concrete will provide protection and separation for people traveling by bike.
Raised Bike Lanes are protected bike lanes raised to sidewalk level and separated from the parking lane.
Floating Bus Stops are sidewalk bump outs that provide dedicated waiting and boarding areas for bus riders, while streamlining bus service and improving accessibility by enabling the bus to stop in the travel lane rather than having to pull over to the curb. Floating bus stops are separated from the sidewalk by a bike lane, eliminating conflicts between buses and bikes at stops and improving safety for people biking. Floating bus stops are constructed like sidewalks with raised concrete areas. All 7 of the bus stops along Western Washington Street will become floating bus stops.
Raised Intersections give priority to people walking by bringing the intersection up to sidewalk level. Raised intersections reinforce slow speeds and encourage people driving to yield to people in the crosswalks. There will be raised intersections on Washington Street at Skehan Street, Hanson Street at Skehan Street, and Oak Street at Houghton Street.
Raised Crosswalks make crossing the street safer and more comfortable for everyone. Since they are elevated (roughly to sidewalk height), people driving must slow down as they approach the crossing. Because they are sidewalk height, they enable people using wheelchairs and other mobility devices to cross more easily. There will be 4 raised crosswalks across Washington Street, 5 raised crosswalks across side streets that intersect Washington Street, and 1 raised crosswalk on Perry Street at Lincoln Park.
Speed humps are asphalt traffic-calming devices intended to reduce vehicle speeds to 10 to 15 mph. We paint them with white triangles and yellow stripes and place signage nearby to ensure they are visible to approaching vehicles. Speed humps are typically placed 200 feet apart to prevent people from speeding in between them. Speed humps maintain access for residents, first responders, and services such as street sweeping, snow removal, and deliveries. Speed humps will be added on Dane Street, Calvin Street, Perry Street, Wyatt Street, Concord Avenue, and Newton Street.
Pedestrian Signals are dedicated lights at intersections for people crossing in the crosswalk. New pedestrian signals will be added to the intersection of Calvin Street, Dane Street and Washington Street.
Construction
Construction on Washington Street is scheduled to begin in 2023 and be completed by November 2024. City contractors will start on sidewalk reconstruction and then move to repaving the roadway and installing the new traffic calming features such as raised crosswalks and sidewalk curb extensions.
To stay up to date on construction, sign up for City Alerts available via phone call, text, or email at somervillema.gov/cityalerts. You can also sign up for the City Construction Newsletter at somervillema.gov/construction. Regular updates will be posted on this project website. If you have any questions during construction, reach out to construction@somervillema.gov or 617.981.2896.
-
February 2023 Update
Share February 2023 Update on Facebook Share February 2023 Update on Twitter Share February 2023 Update on Linkedin Email February 2023 Update linkThank you to all who took the Western Washington Street Design Feedback Survey in October, attended the virtual public meetings in 2022, sent in email comments, or spoke to us at our street pop-ups. We appreciate hearing your feedback on transportation needs in the area, traffic safety concerns along Washington Street and around Ward 2, and your comments on the proposed reconstruction designs.
Feedback
Below is a summary list of what we heard in feedback about the proposed designs. You can also check out the survey summary report that summarizes what we heard in the design feedback survey.
Transit
Recognize that there is a strong push for protected bike lanes, but don’t want to forget about bus riders
Support from some who identified as transit riders for bus lane approaching Union and Dane St since it cuts through car congestion
Some support for consolidation of bus stops to reduce bus delay, and some concern over the placement of the consolidated bus stops
Urged to continue to do outreach to bus riders
Interest in improving the waiting experience at bus stops with amenities like benches or shelters
Bike facilities
Enthusiastic support for protected bike lanes
Skepticism about bus/bike lane as an option for people of all ages and abilities
Washington Street described as an important connector to other bike facilities and key destinations like Union Square
Right turn out of Dane Street is heavily used for both people biking and driving and needs attention
Desire to provide safe ways to make left turns from Washington Street
Dangerous turning conditions at Beacon Street and Washington Street
Pedestrian facilities
Concerned about sidewalk condition and walking safety issues on nearby Hawkins Street due to speeding
Support for the increase in crosswalks proposed in the designs, with some asking for more crosswalks
Enthusiastic support for better sidewalks, especially as it improves access for people with mobility impairments or people traveling with children or strollers
Support for traffic calming facilities like raised crosswalks to reduce speeding vehicles, especially at key destinations such as Perry Park and Lincoln Park
Desire for additional raised crosswalks on adjacent streets, albeit these might be outside of the scope of the project
Advocacy for wider sidewalks when possible
Request for yellow flashing lights at crosswalks; audible crosswalk lights
Request for raised crosswalk at school entrance
Driving/Parking
Some support shared from people who drive – they like the clarification of bike movements and better visibility
Concern for teacher parking options near the Argenziano
Concern for increased frustration for people driving experiencing more congestion or being forced to go slower
Requests for loading zones and short-term parking options near businesses
Concern with the reduction of parking along the street
Desire for more accessible spaces with curb ramp access
Greenery
Desire for more trees and green space wherever possible
Requests to explore options for more trees around bus stops to make it easier while waiting in the sun
Advocacy to enlarge tree pits to provide more space to trees
Maintenance
Enthusiastic support for repaving the road and fixing the sidewalks
Reiterated need for continued maintenance to keep new protected bike lanes clear of debris and snow
Speed humps
The City initially identified Dane Street, Calvin Street, and Perry Street as candidates for speed humps. In the survey, 74% shared that they really support installing speed humps on these streets
Additional streets that residents asked the City to consider included Concord Ave, Newton St, Lake St, and Village St
Some concerned about installing any speed humps as they can be uncomfortable to drive over
Next Steps
The City Council’s Finance Committee approved funding of the upcoming street and sidewalk reconstruction package that includes the Western Washington Street improvements. The package also includes the completion of the Holland and College Mobility Improvements project street repaving and sidewalk reconstruction for Meacham Road.
Along with street reconstruction, this package includes the installation of approximately 20-30 speed humps. Speed humps are traffic-calming devices intended to reduce vehicle speeds. These asphalt structures are 3-4 inches high. Speed humps are typically placed about 200 feet apart to prevent people from speeding in between them. Speed humps significantly reduce speeding while maintaining access for residents, services, deliveries, and first responders. Speed humps do not impact drainage, street sweeping, snow removal, or street parking. When selecting streets for speed humps, we first review any available speeding or traffic volume data that has been collected on the street. We look at a street’s design and if it has large distances between when a vehicle needs to stop at a stop sign, crosswalk, or traffic light. And then we prioritize streets that are next to schools, parks, and community path crossings. We place speed humps on streets that are relatively flat and straight.
The streets that are being proposed for speed humps in this package that are in Ward 2 include:
Dane Street
Newton Street - between Webster Ave and Springfield Street
Perry Street
Wyatt Street
Calvin Street
Concord Ave - between Beacon Street and Springfield Street
Now that City Council has approved the project financing, the next step is to secure a contractor to perform the construction work. In the meantime, City staff are developing final plans for Western Washington Street and incorporating the feedback we heard from the community. We will post the final plans on this website later this spring. The construction start date has not yet been determined but could begin anytime between Spring 2023 and Spring 2024.
If you haven’t already done so, please subscribe to the Mobility Monthly Newsletter to get email updates about Somerville transportation planning projects, like the Western Washington Street project, and signup for City Alerts to receive notifications on construction, special events, and snow emergencies via text, phone call or email. If you have any questions, please reach out to the team at transportation@somervillema.gov.
Who's Listening
-
Email rwright@somervillema.gov -
Phone 617-981-2896 Email jmoos@somervillema.gov -
Construction Public Information Officer
NAEmail nalakel@somervillema.gov
Documents
- First Community Meeting Presentation Slides (Mar 1, 2022) (5.43 MB) (pdf)
- Second Community Meeting Presentation Slides 9.28.22 (7.7 MB) (pdf)
-
Community Meeting #2 Flyers
- West Wash Public Meeting 2 Flyer (English) (1.36 MB) (pdf)
- West Wash Public Meeting 2 Flyer (Haitian Creole) (1.36 MB) (pdf)
- West Wash Public Meeting 2 Flyer (Nepali) (1.38 MB) (pdf)
- West Wash Public Meeting 2 Flyer (Portuguese) (1.36 MB) (pdf)
- West Wash Public Meeting 2 Flyer (Simplified Chinese) (1.62 MB) (pdf)
- West Wash Public Meeting 2 Flyer (Spanish) (1.36 MB) (pdf)
- West Wash Public Meeting 2 Flyer (Traditional Chinese) (1.64 MB) (pdf)
- Survey and Public Input Engagement Report Western Washington Street August 2022 (424 KB) (pdf)
- Design Feedback Survey Report Western Washington Street Mobility Improvements Fall 2022 (594 KB) (pdf)
-
Final Proposed Designs Materials
- Western Washington St and Ward 2 Proposed Final Designs Map (6.35 MB) (pdf)
- Rendering of final design on Washington Street at Rose Street (9.04 MB) (png)
- English West Wash Final Designs Brochure 2023 (9.85 MB) (pdf)
- Spanish West Wash Final Designs Brochure 2023 (9.86 MB) (pdf)
- Portuguese West Wash Final Designs Brochure 2023 (9.86 MB) (pdf)
- Haitian Creole West Wash Final Designs Brochure 2023 (9.86 MB) (pdf)
- Nepali West Wash Final Designs Brochure 2023 (10 MB) (pdf)
- Simplified Chinese West Wash Final Designs Brochure 2023 (10.2 MB) (pdf)
- Traditional Chinese West Wash Final Designs Brochure 2023 (10.3 MB) (pdf)
- 2023-07 100% Plans (31.4 MB) (pdf)
- 2023-09 Revision 100% Plans.pdf (46.2 MB) (pdf)
- July 2023 Traffic Commission Meeting Items for Western Washington St (5.73 MB) (pdf)
-
Final Design Illustrations
- Washington St Final Design Illustration (English) (6.34 MB) (pdf)
- Washington St Final Design Illustration (Haitian Creole) (6.35 MB) (pdf)
- Washington St Final Design Illustration (Nepali) (6.36 MB) (pdf)
- Washington St Final Design Illustration (Portuguese) (6.35 MB) (pdf)
- Washington St Final Design Illustration (Simplified Chinese) (6.58 MB) (pdf)
- Washington St Final Design Illustration (Spanish) (6.35 MB) (pdf)
- Washington St Final Design Illustration (Traditional Chinese) (6.61 MB) (pdf)
Subscribe to Mobility Email Updates
Key Dates
-
March 01 2022
-
September 28 2022