Broadway Magoun Reconstruction Project
Background
As part of the Pavement and Sidewalk Management Program, the City of Somerville plans to reconstruct sidewalks and repave Broadway from Winchester Street to Central Street. With the opportunity to reconstruct the street, we want to develop a new street design that will increase safety, improve accessibility, incorporate more sustainability and plant life, and create a more comfortable street.
We aim to do this by:
- Reconstructing all the sidewalks along Broadway from Winchester Street to Central Street, along with approximately 20 feet into intersecting street
- Repaving the street from sidewalk curb to sidewalk curb
- Adding accessible curb ramps and tactile warning pads to all existing crosswalks
- Exploring opportunities for new crossings and improved crossings such as installing raised crosswalks/intersections or curb extensions
- Identifying locations for new trees and considering improvements for existing trees such as expanded tree wells and tree bump-outs to support tree longevity and health
- Upgrading existing bicycle facilities to provide protection
- Making improvements to traffic signal operations at signalized intersections
- Considering traffic calming like speed humps on streets in the nearby area
This segment of Broadway is designated for protected bike lanes in both directions as part of the Somerville Bicycle Network Plan and required by the Safe Streets Ordinance.
Anticipated Timeline
From October through November 2025, we will work to gather feedback from community members about transportation safety concerns and priorities for the future of this section of Broadway. Over the winter, we will develop a concept design shaped by the feedback we heard and the data we analyzed such as vehicle speeds, vehicle volumes, bus ridership, traffic signal operations, and pedestrian and bicycle counts. In Spring 2026, we will publish a concept design and conduct another round of community engagement. Over the summer of 2026, we will work to refine the design to bring an updated version in Fall 2026 for final community feedback. We will then work to finalize the design and prepare for construction between 2027 and 2029.
Information in Other Languages
Spanish - La ciudad de Somerville puede proporcionarle un intérprete en su idioma de forma gratuita. Para solicitar un intérprete, comuníquese con nosotros a través de languageaccess@somervillema.gov o llame al 311 (617-666-3311) al menos con 7 días de anticipación al evento.
Portuguese - A Prefeitura de Somerville pode fornecer um intérprete em seu idioma gratuitamente. Para solicitar um intérprete, entre em contato conosco por languageaccess@somervillema.gov ou ligue para 311 (617-666-3311) com pelo menos 7 dias de antecedência ao evento.
Haitian Creole - Vil Somerville ka ba ou yon entèprèt nan lang ou gratis. Pou mande yon entèprèt, tanpri kontakte nou nan languageaccess@somervillema.gov oswa rele 311 (617-666-3311) omwen 7 jou davans evènman sa a.
Nepali - समरभिल सिटिले तपाँईलाई तपाँईको भाषामा नि:शुल्क अनुवादक उपलब्ध गराउन सक्छ। अनुवादक अनुरोध गर्न कृपया हामीलाई कार्यक्रमको कम्तिमा ७ दिन अगाडि languageaccess@somervillema.gov मा इमेल मार्फत वा ३११ (६१७-६६६-३३११) मा फोन मार्फत सम्पर्क गर्नुहोस्।
Traditional Chinese - 薩默維爾市政府可以免費提供您所說的語言的口譯。如需要口譯服務,請於活動前最少7日發送電郵至 languageaccess@somervillema.gov 或撥打 311 (617-666-3311) 提出申請。
Simplified Chinese - 萨默维尔市政府可以免费提供您所说的语言的口译。如需要口译服务,请于活动前最少7日发送电邮至 languageaccess@somervillema.gov 或拨打 311 (617-666-3311) 提出申请。